“Last pile is in. Done and dusted. Thanks to all involved!” – Victor Donchenko, Captain of the Seaway Heavy Lifting.
This weekend, a new milestone was reached in the construction of wind farm Hollandse Kust Zuid; all 140 monopiles were piled into the Dutch North Seabed.
Mary Carol Anderson, foundation installation Manager, reflects on the milestone:
“A big achievement by the project team, our contractors – Seaway Heavy Lifting & SIF – and all other parties involved. Going from installing 34 foundations in the 2021 summer campaign, to installing 106 foundation in 2022, is a huge testament to the team!”
The project will soon publish a more extended reflection on the past piling campaign later this month.